INJURY AT SEA IS OPEN FOR BUSINESS. Our staff is working remotely until further notice to help protect our employees, clients, and our communities from the novel coronavirus (COVID-19). Our legal team will be answering calls, voicemail, and email, and will conduct all business by telephone, video conference, email or other electronic means. IF YOU HAVE BEEN INJURED AT SEA WE ARE STILL HERE TO HELP! We are still available 24/7 to talk about your case. We appreciate your patience until we are able to resume full and normal operations of all of our offices. We will get through this together!

Damage to lock worse than thought

The large Ballard lock is still operating on a twice-daily basis as crews work for fix damage from a lightning strike that turned out to be worse than initially thought.

A powerful blast of lightning knocked out power to the large lock shortly before midnight almost three weeks ago. Three days later, on Oct. 14, the U.S. Army Corps of Engineers reopened the lock on a limited basis, with openings at 9 a.m. and 1 p.m. daily.

Workers have been stationed underground on either side of the lock, operating the miter gates that hold and release water by using an electrical crank system that operates separately from the main electrical box, which was knocked out by the lightning strike. The lock still can’t be operated from the above-ground tower.

The large lock is scheduled to close for annual maintenance between Nov. 10 and 24. Crews are expecting additional parts needed for repairs to arrive today, Graesser said, and the Corps hopes to have the large lock fixed and reopened before the maintenance starts.

In the meantime, the lock will continue to be opened twice a day. Barges and freighters on scheduled runs will get priority for one space per company for each opening, with other commercial vessels given the next priority. If there is room, recreational vessels will be allowed to use the large lock.